2024

Rodeo TravelGround-Up Construction

JF completed the full construction of the Rodeo Travel Center in Pleasanton, TX, from the ground up. This expansive project, led by our dedicated San Antonio team, included the installation of industry-leading fueling systems, a comprehensive tank setup, and durable canopies. The completed site features 16 Gilbarco Encore 700 dispensers, 6 TA truck dispensers, a Veeder-Root TLS 450 monitoring system, and various Watco tanks designed to accommodate different fuel needs.

 

IMG_0238 copy
The Challenge

COMPLEX REQUIREMENTS MET

The Rodeo Travel Center required a fuel setup that could serve both light vehicles and heavy-duty trucks, with an emphasis on efficiency and versatility. Each fueling island needed the right combination of dispensers, DEF units, and compliant equipment to meet both Valero and TA branding specifications, all while aligning with environmental standards and user safety.

 

IMG_0236 copy
IMG_0233 copy
The Solution

COMPREHENSIVE SYSTEM INSTALLATION

JF’s team installed a robust fueling system tailored to high-volume traffic and diverse fuel types. The setup included 16 Gilbarco Encore 700 dispensers, 6 TA truck dispensers, and canopies for weather protection. A Veeder-Root TLS 450 tank monitoring system and Watco tanks, including a split 40K tank for multiple fuel types, ensured smooth operations, reliable monitoring, and long-term asset protection.

The Outcome

SUCCESSFUL PROJECT COMPLETION

The project was successfully completed, and the Rodeo Travel Center is fully operational. The site is now equipped to serve a wide range of fuel needs, providing quick and secure service to drivers while ensuring environmental safety and operational efficiency.

Screenshot 2024-11-11 144805 copy
IMG_0235 copy

KEY COMPETENCIES

Comprehensive Fueling Systems

Designed and installed advanced fueling systems with multiple dispensers to support high-volume use.

Environmental Compliance

Implemented a Veeder-Root TLS 450 for precise monitoring, ensuring compliance with environmental standards.

Durable Infrastructure

Constructed resilient canopies and protective features that extend the longevity of the fueling equipment.

Project Management Excellence

Coordinated complex tasks across multiple teams, delivering the project within the established timeline and scope.